KEMPOWER DC Installation
Bascon Group was selected to install all electrical works pertaining to the new EV chargers for the Monash bus interchange. Bascon was the primary contractor incharge of all Civil and Electrical works working in to deliver the project for Monash and Engie.
The design of this project was worked closely with the Monash University design team to ensure the Bus Interchange maintained a high appearance standard. To maintain the standard of design, all works on concrete was required to be sandblasted to achieve the correct finish as well as crosscuts to match the existing Bus Interchange.
Services provideD
Project Management
Civil Construction
Electrical Installation of DC Chargers
Traffic Management
Project Summary
Day 1
Delivery of skip bins for the removal of concrete
Concrete cutting is completed an easier removal of the concrete
Concrete is then excavated and placed into the skip bins on site
Skip bins are then removed from site
Day 2
NDD (Non-Destructive Digging) is completed to allow for the underground conduits to be installed
Underground electrical conduits are then installed for the wiring of the EV charger
Crushed rock is backfilled in preparation for concreting the next day
Satellite is leveled out to ensure proper delivery of the project
Day 3
Concrete is then poured and completed ready for decorative crosscuts
Concrete is also poured to an existing conduit location
Rectifiers & Satellites are also painted by our qualified painter to the clients specific requested colour
Day 4
Decorative crosscuts completed to match existing design of bus interchange
Protective bollards are installed in front of EV satellites to ensure no damage is inflicted on the satellites
Day 5
Commissioning of satellites is completed
Final site walkthrough
All final equipment removed off site
Final site clean up & opening the closed area to the public