Day 1
Delivery of skip bins for the removal of concrete
Concrete cutting is completed an easier removal of the concrete
Concrete is then excavated and placed into the skip bins on site
Skip bins are then removed from site
Day 2
NDD (Non-Destructive Digging) is completed to allow for the underground conduits to be installed
Underground electrical conduits are then installed for the wiring of the EV charger
Crushed rock is backfilled in preparation for concreting the next day
Satellite is leveled out to ensure proper delivery of the project
Day 3
Concrete is then poured and completed ready for decorative crosscuts
Concrete is also poured to an existing conduit location
Rectifiers & Satellites are also painted by our qualified painter to the clients specific requested colour
Day 4
Decorative crosscuts completed to match existing design of bus interchange
Protective bollards are installed in front of EV satellites to ensure no damage is inflicted on the satellites
Day 5
Commissioning of satellites is completed
Final site walkthrough
All final equipment removed off site
Final site clean up & opening the closed area to the public